Whenever an application is made for a permit provided in this title or any related ordinance of the city of North Bend which is required for a development project, then the applicant may elect to have any and all permits from the city processed at one time, and procedures may be consolidated as required or permitted by Oregon law and city ordinances. All discretionary land use applications or combinations of discretionary land use applications shall be processed and final action taken by the city, including appeals provided in city ordinances, within 120 days after the applications are deemed complete, except that the city shall take final action on housing applications meeting the criteria of ORS 197.311 within 100 days. (Ord. 2025 § 18, 2018; Ord. 1952 § 1(4), 2006)